Lied to yet again about getting our street flooding and erosion problem taken care of...8 yrs now, we were to be on the list to be done by this OCT, now some other B S story, lie lie lie, this county is the worst for its taxpayers....I want my road fixed, big mini lakes in front of mailboxes and driveways during rain storms. Cannot walk down the street due to the puddles...Lie Lie Lie.
20 Comments
Pinellas County Communications (Verified Official)
Jsmekal (Registered User)
Godkänd Pinellas County Public Works (Verified Official)
The issue you reported to Pinellas County - SeeClickFix, has been forward to Karen Ballard and she called and spoke with and informed your husband with the current schedule information. Thank you and have a nice day. Thank you for your input!
We are striving to improve our services. Please take a moment to tell us how we are doing. Your input is greatly appreciated, thank you!
link: https://www.surveymonkey.com/s/Survey_PublicWorks
Stängt Pinellas County Public Works (Verified Official)
Marianne GAeta (Registered User)
Reopened Marianne GAeta (Registered User)
Godkänd Pinellas County Communications (Verified Official)
Stängt Pinellas County Communications (Verified Official)
Reopened Marianne GAeta (Registered User)
Pinellas County Communications (Verified Official)
Marianne GAeta (Registered User)
Godkänd Pinellas County Communications (Verified Official)
Here is a status of the project.
• The Project # is 001177A
• The Preliminary Engineering Report was completed in the fall of 2015, and identified several roads that needed surface improvements and drainage improvements.
• All roads within Lakeshore estates are in need of resurfacing, however, we only focused on those requiring drainage improvements
• We identified 5 roads that had significant drainage and road repair issues, they are all or portions of Citrus Drive, Cypress Drive, North Canal, South Canal and Freshwater Drive.
• We have an agreement with HDR Engineering (consultant) to provide the final design and permitting for these 5 roads (or sections of roads). Both North and South Canal were identified as needing drainage and road repairs for entire road segments.
• The consultant has completed survey and road condition assessment, including geotechnical borings of underlying soils, which is important to designing the road repairs.
• We are at the 30% design stage. Issues associated with poor soils under most of the roads are causing us to explore alternatives to resurfacing
• We expect to be done with the design and permitting for all 5 roads by early 2017 (February)
• The plan at this time is to go forward with construction for all 5 roads (funding being the issue). As this may exceed internal thresholds, the job will most likely go out for bid.
• Construction bid package is currently estimated to go forward in spring 2017 with construction in summer of 2017.
This is as close we can project construction, at this time.
Call if you have any questions.
Bruce Wirth, P.E.
Sr. Engineer
Supervisor, Stormwater Section, Public Works
14 S. Fort Harrison Ave., 4th Fl,
Clearwater, FL 33756
Phone (727) 453-3469
FAX (727) 464-3595
bwirth@pinellascounty.org
Stängt Pinellas County Communications (Verified Official)
Reopened Marianne GAeta (Registered User)
Pinellas County Communications (Verified Official)
Godkänd Pinellas County Communications (Verified Official)
Pinellas County Code Enforcement (Verified Official)
Pinellas County Public Works (Verified Official)
Pinellas County Public Works – Stormwater, Urban Forestry, Landscape Svcs & Vegetation Maintenance (Verified Official)
Thank you for taking the time to “Report an Issue” via Doing Things for you! The project design is near complete and what impacted the construction schedule is the project cost which significantly increased over original estimates. Public Works is finalizing the FY18 budget with the goal of allocating the necessary funds. Ms Gaeta, please reference PID001177A when checking on the status of this report. This SeeClickFix will remain open and monitored for any future comments.
We are striving to improve our services. Please take a moment to tell us how we are doing. Your input is greatly appreciated, thank you! link: www.pinellascounty.org/surveys/PublicWorks
Stängt Pinellas County Public Works – Stormwater, Urban Forestry, Landscape Svcs & Vegetation Maintenance (Verified Official)